This
millennium-funded project saw the original hall demolished leaving only the
foundations and floor slab.
The new
cedar clad timber framed hall was built round a portal steel frame and was
extended to provide a new stage and conservatory area. To create a feature
to the front of the building, the conservatory was built of a beam and block
floor suspended on the steel frame.
The
steeply pitched roof, clad with steel profile insulated composite panels,
providing adequate height to play badminton in the hall area.
|